Confirmed Net Impact
$58,550
Approved
$30,150
Processed
$18,900
Pending Confirmation
2 records
Open Changes
4
StatusChange #DescriptionCostTrade PartnerReferenceScheduleResponsibleAttention
CR-001
Added lighting at third-floor restrooms
PC
RFI-042
PCPricing NeededResponse NeededFollow-Up DueOverdueSchedule Impact Unknown
CR-002
Rock excavation at east footing line
Approved
credit ($4,000)
net $11,250
PCO-011
Not Processed
CR-003
Mechanical shaft reroute at Level 2
Quoted
PCO-014
Response NeededMissing Documentation
CR-004
Plumbing fixture upgrade — Allowance #02
Processed
OCO-003
CR-005
Additional lighting third floor restroom package
PC
PCSchedule Impact UnknownPossible Duplicate